Market brief for Secretariat Dubai

Only 8.5% of big projects hit their time and cost targets

Delay analysis decides who pays for the other 91.5%. Eight projects, four sectors, one question: whose delay was it?

A forest of tower cranes at the Hinkley Point C nuclear construction site in Somerset
Hinkley Point C, Somerset. Photo: Roger Cornfoot / geograph.org.uk via Wikimedia Commons, CC BY-SA 2.0

vizmaya desk · 29 November 2026

how late, how costly
The terminal building of Berlin Brandenburg Airport seen from the forecourt
Berlin Brandenburg Airport opened in 2020, about 9 years late. Photo: Arne Müseler / Wikimedia Commons, CC BY-SA 3.0 de

Eight projects ran up to 13 years late

Late is normal at this size. Hinkley Point C now targets 2030. Its first target was 2017.

Sources: The Guardian, Severn Estuary Interests Group, Wikipedia, Business Insider, Forbes, E&E News, Luxuo, BBC. Hinkley is a forecast. Kashagan is "more than 8". Crossrail runs Dec 2018 to May 2022.

The Sydney Opera House sail roofs on the harbour
Sydney Opera House. Photo: Dietmar Rabich / Wikimedia Commons, CC BY-SA 4.0

Delay carries a bill: 14.6x for the Opera House

McKinsey reviewed 300+ projects over $1 billion. Average cost overrun: about 80%. Average schedule delay: about 50%.

Sources: Wikipedia (A$7M to A$102M), FX Design, Luxuo, The Guardian, E&E News, McKinsey. Nominal figures. Hinkley mixes 2016 and 2015 price bases.

US disputes now average $56.0M vs $16.3M in 2018

That is 3.4 times higher. Delays and time extensions are now a top-3 cause of disputes.

Arcadis expects more disputes in 2026. The average dispute lasts 12.2 months vs 17.6 in 2019.

Source: Arcadis, 16th Annual Construction Disputes Report, US edition, 2026.

how a delay gets analysed

What a delay analyst does

A project planned one finish date. It hit a later one. The analyst finds which events caused the gap, and whose they were.

Then the gap gets a price. That is where claims and arbitration start.

Sources: Secretariat; AACE RP 29R-03.

Learn it on a road trip

Our own trip plan said 5 hours. The road disagreed. Taking 9 hours is a 4-hour delay.

The road closure lasted 3 hours. The flat tire lasted 2. They overlapped for 1, so together they cost 4 hours, not 5.

Illustration with invented numbers. The critical path is the chain of tasks that sets the finish date.

Nine ways to ask the same question

AACE lists nine methods. Some read the schedules that exist. Others rebuild a schedule and test it.

Read the schedules

Static: compare two pictures
  • 3.1Plan vs actual, in one go
  • 3.2Plan vs actual, period by period
Dynamic: follow the updates
  • 3.3Windows: step through each update
  • 3.4Windows with the causes split
  • 3.5Windows with missing updates rebuilt

Rebuild and test

Additive: put the delays in
  • 3.6Add delays to the plan
  • 3.7Time impact: add them one at a time
Subtractive: take the delays out
  • 3.8Remove delays from what happened
  • 3.9The same, window by window

The SCL Protocol, second edition, lists six methods. It prefers none.

Sources: Long International, ScheduleInsight, 5 Mar 2026. AACE RP 29R-03, rev. 2011.

One hour, two owners. Who pays?

That purple hour had two causes at once. Experts call it concurrent delay.

One expert paper says methods 3.1 to 3.5 usually handle it poorly. It adds that in most US jurisdictions, neither side then typically gets delay damages.

The method you pick decides how that hour is counted.

Source: Long International, "AACE 29R-03 Schedule Analysis Methods".

what it means

No updates, no windows

Windows analysis needs a full set of credible schedule updates. Without them, that method is off the menu.

Arcadis respondents rank accurate, timely schedules second for settling disputes early.

Size matters too. The SCL Protocol says the method must fit the amount in dispute.

Sources: ScheduleInsight; Arcadis 2026.

The Barakah nuclear power plant reactor buildings in Abu Dhabi, UAE
Barakah Nuclear Energy Plant, UAE. Photo: Wikiemirati / Wikimedia Commons, CC BY-SA 4.0

In the Gulf, big builds open in phases

Barakah Unit 1 began commercial operation in April 2021. Units 2, 3 and 4 followed in 2022, 2023 and 2024.

Dubai Metro's Red Line opened on 9 September 2009 with 10 of 29 stations. Jebel Ali station followed on 11 March 2011.

Each section can carry its own completion date. So each can carry its own delay.

Sources: Energy Institute, EWEC, Wikipedia.

New tools, same basics

Arcadis found owners, contractors and advisors investing in digital tools and AI to manage risk.

Its warning: new tools bring new problems when poorly used. Disciplined fundamentals still decide outcomes.

On 23 July 2026, Secretariat and ACEDS reported near universal AI use across the legal industry.

Sources: Arcadis 2026; Secretariat and ACEDS AI Report 2026.

What it means for the market

  • More disputes are expected in 2026.
  • Delay is now a top-3 cause of US disputes.
  • Average value: $56.0M vs $16.3M in 2018.
  • Records decide which methods an expert can use.

Read every big project as a plan, a record and a price tag.

Sources & method

  • Benchmark: McKinsey on Bent Flyvbjerg's database of 16,000 projects; Oxford Saïd.
  • Disputes: Arcadis 2026, US edition only.
  • Methods: Long International, ScheduleInsight. Practice: Secretariat.
  • Project figures are from the press sources under each chart. Costs are nominal, not inflation-adjusted.
  • Images: Roger Cornfoot (CC BY-SA 2.0), Arne Müseler (CC BY-SA 3.0 de), Dietmar Rabich (CC BY-SA 4.0), Wikiemirati (CC BY-SA 4.0), via Wikimedia Commons.
  1. Late is the norm

    Only 8.5% of 16,000 projects hit both cost and schedule targets. Delay analysis decides who pays for the rest.

  2. Up to 13 years late

    Eight projects across buildings, infrastructure, power and oil and gas. Hinkley Point C now targets 2030, not 2017.

  3. Delay carries a bill

    The Opera House cost 14.6 times its first estimate. Hinkley Point C stands at 1.9 times and is still building.

  4. The bill goes to dispute

    The average US dispute was worth $56.0M in 2025, vs $16.3M in 2018.

  5. Enter the delay analyst

    One job: find which events moved the finish date, and whose they were.

  6. A road trip explains it

    Five hours planned, nine taken. Two problems overlapped for one hour.

  7. Nine methods, one question

    Some read the schedules. Others rebuild one. No single method is preferred.

  8. One hour, two owners

    Concurrent delay is where methods disagree. The choice of method decides who owns that hour.

  9. Records pick the method

    No contemporaneous updates means no windows analysis. Project controls today set the options tomorrow.

  10. Closer to home

    Barakah and Dubai Metro opened in phases. Each phase can carry its own delay.

  11. New tools, same basics

    AI is spreading fast. Arcadis says disciplined fundamentals still decide outcomes.

  12. What it means

    More disputes, bigger disputes, and delay as a top-3 cause. Records decide the method.

  13. The whole board

    Every number has a source. The last card holds the links and image credits.